From incoming tube inspection to export packing — the eight production steps behind every finned tube we ship.

1. Incoming material inspection
Every base tube and fin strip is checked against its mill certificate: grade, heat number, dimensions and surface condition. Tubes with laps, seams or excessive ovality are rejected before they reach a machine.
2. Tube preparation
Tubes are cut to length, ends are squared and, where required, the surface is cleaned. For welded products the weld area is degreased to avoid porosity.
3. Fin forming
| Product | Equipment |
|---|---|
| Extruded fin | Three-roller extrusion head, one pass per tube |
| Embedded G fin | Grooving head plus rolling head |
| L / LL / KL fin | Winding machine with tension control |
| HF welded fin | High-frequency welder with strip feed |
| Laser welded fin | Fibre laser welding head on a rotating axis |
| Integral fin | Rolling head with internal mandrel |
4. In-process inspection
Fin height, pitch and thickness are measured every batch; the finned length and bare end lengths are checked against the drawing. For welded products the weld bead is inspected visually and, where specified, by penetrant or ultrasonic methods.
5. Heat treatment and surface treatment
Stress relief is applied for alloy steel products where the specification requires it. Optional surface treatments include hot-dip galvanising, epoxy or phenolic coating, and pickling and passivation for stainless steel.
6. Pressure and leak testing
Hydrostatic testing to 1.5 times design pressure, or pneumatic testing where water is not permitted. Test pressure, hold time and results are recorded per bundle.
7. Dimensional and documentation review
Final dimensional check, visual inspection and a documentation pack: mill certificates, inspection reports, test records and packing list.
8. Packing
Tubes are bundled, end-capped, wrapped in VCI film and packed in sea-worthy wooden cases. Long tubes are supported to prevent sagging during ocean transport.
Request a quality plan for your order
Tell us the tube diameter, fin height, fin pitch, materials and quantity — we reply with price and lead time within one working day.